02 |
LayersLearn more about what we are working on.
|
||
|
Layer 01 ManagementList of Deliverables Work Package 1: Management |
WP1 D.1.1.1 Project Management/ Meetings
WP1 D.1.1.2 Financial Management WP1 D.1.1.3 External Audits |
COMPLETED
COMPLETED 31 May 2020 |
|
Layer 02
Publicity
List of Deliverables
Work Package 2: Information and Publicity
|
WP2 D.2.1.1 Information & Communication Plan
WP2 D.2.1.2 Contribution to project’s website development and social media platforms WP2 D.2.1.3 Public Engagement: Presentation of PALIMPSEST in academic and educational contexts WP2 D.2.1.4 Newsletters WP2 D.2.1.5 Organization of Info-Day 1 |
COMPLETED
COMPLETED 31 May 2020 PENDING 31 March 2019 |
|
Layer 03 Map and AppList of Deliverables Work Package 1: Map and App development |
WP3 D.3.1.1 Mapping Database setup: collection and categorization of pre-existing material, design of mapping layersWP3 D.3.1.2 Contribution to the definition of user requirements through questionnaires, elaboration of results
WP3 D.3.1.3 App design and development for the collection and presentation of crowsourced material to the map WP3 D.3.1.4 Launching of the MAP and APP: setup of tools and services for data collection, presentation and manipulation by the public WP3 D.3.1.5 Elementary Schools’ crowd-sourcing workshops inquest for transgenerational, collective memory narratives (in Greece) |
31 March 2019
31 March 2019 PENDING PENDING 15 July 2019 |
|
Layer 04 Art installation designList of Deliverables Work Package 1: Art installation design |
WP4 D.4.1.1 Elaboration of collected material in Greece. Analysis of temporal and spatial characteristics of crowd-sourcing stories.WP4 D.4.1.2 Planning and selection of areas in Greece for implementation. Construction of cartographical narrative: ArtPlot in Map
WP4 D.4.1.3 Calibration of pre-existing material and crowd-sourced narratives and plot to space time specifications, in Greece WP4 D.4.1.4 Competition and workshop for the design of artistic, interactive, site-specific installations to be selected for implementation WP4 D.4.1.5 Specification of technical requirements for the implementation of the artistic installations on site |
30 November 2019
30 November 2019 30 November 2019 29 February 2020 29 February 2020 |
|
Layer 05 Art installation implementationList of Deliverables Work Package 1: Implementation of interactive installations and connection to map and app |
WP5 D.5.1.1 Construction of interactive, artistric installations (in Greece)WP5 D.5.1.2 Implementation and adaptation of interactive, artistic installations in selected sites (in Greece) WP5 D.5.1.3 Testing, calibration and corrective actions for the mise-en-scene of the interactive, artistic installations WP5 D.5.1.4 Overall connection of installations to the app and mapping database WP5 D.5.1.5 Overall testing and valorization |
30 April 2020
30 April 2020 30 April 2020 31 May 2020 31 May 2020 |
|
Layer 06
Stories
List of Deliverables |
|